Job Description | |||||||||
Providing , installation of M.S sandwich full length pice panel Sheet 50mm mm thick ( Pre painted ) over M.S frame structure using hex washer head self tapping & drilling screws and over laping G.I Sheet 24-SWG at corners painted with matching colour i/c carriage of material from lahore to Gojra at site of work through Container/troller , charges of uplifting through crane at 40' height for installation, cost of all other materials , labour etc complete in all respects as per drawing and design as approved and advised by the Consultant / Engineer In charge. | |||||||||
(1st BI-ANNUAL-2017 , 01.01.2017 TO 30.06.2017) | |||||||||
Unit: | P. Sft | Take for analysis= 37.5' x 45'=1687.5 Sft | |||||||
S. No. | Description | Unit | Quantity | Rate | Amount | ||||
A | Materials | ||||||||
1 | M.S Sandwich panel sheet full width 38ft. | ||||||||
Top 38' x 37.5' | = | 1425 | Sft | ||||||
Front 37.5' x 2.66' | = | 99.75 | Sft | ||||||
Back 37.5' x 5.66' | = | 212.25 | Sft | ||||||
Add wastage 5 % | 86.85 | Sft | |||||||
Total | = | 1823.85 | Sft | Sft | 1,823.85 | 580.00 | 1,057,833 | ||
G.I Sheet 24 SWG | |||||||||
Front 37.5' x 1' | = | 37.5 | Sft | ||||||
Back 37.5' x 1' | = | 37.5 | Sft | ||||||
Add wastage 5 % | 3.75 | Sft | |||||||
Total | = | 78.75 | Sft | ||||||
78.75 Sft @ 1.156 Lbs/Sft | = | 41.33 | Kgs | Kg | 41.33 | 100.00 | 4,133 | ||
2 | hex washer head self tapping & drilling screws | ||||||||
Top and sides @ 3' c/c | 247 | Nos | |||||||
Add wastage 10 % | 25.00 | Nos | |||||||
Total | = | 272.00 | Nos | Nos | 272.00 | 35.00 | 9,520 | ||
3 | Steel cutting disc | Each | 5.00 | 480.00 | 2,400 | ||||
4 | Electricity | Unit | 75.00 | 20.00 | 1,500 | ||||
Total Amount ( A ): | 1,075,386 | ||||||||
B | Carriage and hire charges | ||||||||
2 | 38' Length roof sheet panel on troller container i/c loading & Unloading | Each | 33% | 30,000.00 | 10,000 | ||||
4 | Drill machine for 3 days @ 300 / day | Day | 3.00 | 300 | 900 | ||||
6 | Crane for uplifting the full length sheet panels and placing them at proper place upto 40' height. | Day | 1.00 | 30000 | 30,000 | ||||
Total Amount ( B ): | 40,900 | ||||||||
C | Labour | ||||||||
(a) | Labour required Fixing M.S Sandwich Panel Sheet. | ||||||||
1 | Technician | ||||||||
1 Nos for 3 days | Days | 3.00 | 2,800 | 8,400 | |||||
2 | Skilled Cooly ( LB-024) | ||||||||
4 Nos for 3 days | Days | 12.00 | 608 | 7,296 | |||||
Add sundries 10% | 1,569.6 | ||||||||
Total Amount ( C ): | 17,266 | ||||||||
Total Amount ( A + B + C ): | 1,133,552 | ||||||||
Contractor profit , taxes , site expenses and over head 20% | 226,710.3 | ||||||||
Grand Total Amount: | 1,360,262 | ||||||||
Rate Per Sft = | 1360262 | 806.08 | |||||||
1687.5 | |||||||||
Say Rs | 806 | P/Sft |
Ad
loading...
Showing posts with label RATE ANALYSIS. Show all posts
Showing posts with label RATE ANALYSIS. Show all posts
Rate Analysis Of M.S sandwich panel Sheet 50mm mm thick
RATE ANALYSIS of HDPE Plan Bend 90 degree
RATE ANALYSIS | ||||||
Job Description | ||||||
Providing /Fixing High Density Poly Ethylene ( HDPE ) Plan Bend 110mm dia (Dadex / Beta / BBJ / or any equivalent) i/c polyfusion joint, solvent solution as approved by the consultant and Engineer Incharge complete in all respect. | ||||||
Unit: | Each | Take for Analysis = 1 No | ||||
S. No. | Description | Unit | Quantity | Rate | Amount | |
A | Materials | |||||
1 | Elbow 90* 110mm ( Rate List attached ) With wastage 10 % | No | 1.10 | 1200 | 1,320 | |
3 | Electricity for Joints Machine( 2 Joints ) | Unit | 5.00 | 20.00 | 100.00 | |
Total Amount ( A ) | 1,420.00 | |||||
B | Carriage and hire charges | |||||
1 | Carriage of matieral at site | Each | 1 /15 | 900 | 60.00 | |
Total Amount ( B ) | 60.00 | |||||
C | Labour | |||||
1 | For Polyfusion welded joint with machine i/c Labour ( as per Market Rate) | Each | 2.00 | 700 | 1,400.00 | |
Total Amount ( C ) | 1,400.00 | |||||
Total Amount ( A + B + C ): | 2,880.00 | |||||
Contractor profit , taxes , site expenses and over head 20% | 576.00 | |||||
Grand Total Amount: | 3,456.00 | |||||
Rate For Each.: | 3,456.00 | |||||
Say: | 3,456 | Each |