Rate Analysis Of M.S sandwich panel Sheet 50mm mm thick


Job Description
Providing , installation of M.S sandwich full length pice panel Sheet 50mm mm thick ( Pre painted ) over M.S frame structure  using hex washer head self tapping & drilling screws and over laping G.I Sheet 24-SWG at corners painted with matching colour  i/c carriage of material from lahore to Gojra at site of work through Container/troller , charges of uplifting through crane at 40' height for installation, cost of all other  materials ,  labour  etc complete in all respects as per drawing and design  as approved and advised by the Consultant / Engineer In charge.
(1st BI-ANNUAL-2017 , 01.01.2017 TO 30.06.2017)
Unit: P. Sft Take for analysis= 37.5' x 45'=1687.5 Sft
S. No. Description Unit Quantity Rate Amount
A Materials        
1 M.S Sandwich panel sheet full width 38ft.          
  Top                    38' x 37.5' = 1425 Sft        
  Front                    37.5' x 2.66' = 99.75 Sft        
  Back                    37.5' x 5.66' = 212.25 Sft        
  Add wastage 5 % 86.85 Sft        
    Total = 1823.85 Sft  Sft         1,823.85         580.00        1,057,833
  G.I Sheet 24 SWG           
  Front                    37.5' x 1' = 37.5 Sft        
  Back                    37.5' x 1' = 37.5 Sft        
  Add wastage 5 %   3.75 Sft        
    Total = 78.75 Sft        
  78.75 Sft @ 1.156 Lbs/Sft  = 41.33 Kgs  Kg               41.33         100.00                4,133
2 hex washer head self tapping & drilling screws           
  Top and sides @ 3' c/c 247 Nos        
  Add wastage 10 %   25.00 Nos        
    Total = 272.00 Nos  Nos            272.00            35.00                9,520
3 Steel cutting disc     Each                 5.00         480.00                2,400
4 Electricity    Unit               75.00            20.00                1,500
  Total Amount ( A ):            1,075,386
B Carriage and hire charges          
2 38' Length roof sheet panel on troller container i/c loading & Unloading  Each  33%    30,000.00              10,000
4 Drill machine for 3 days @ 300 / day   Day                3.00 300                   900
6  Crane for uplifting the full length sheet panels and placing them at proper place upto 40' height. Day                1.00 30000              30,000
  Total Amount ( B ):                  40,900
C Labour           
(a) Labour required  Fixing M.S Sandwich Panel Sheet.         
1 Technician          
  1 Nos for 3 days    Days                 3.00            2,800                8,400
2 Skilled Cooly ( LB-024)          
  4 Nos for 3 days    Days               12.00               608                7,296
  Add sundries 10%                 1,569.6
  Total Amount ( C ):                    17,266
  Total Amount ( A + B + C ):            1,133,552
  Contractor profit , taxes , site expenses and  over head 20%            226,710.3
  Grand Total Amount:                      1,360,262
  Rate Per Sft   = 1360262                      806.08
1687.5    
              Say Rs        806  P/Sft 