Brick floor
The floor whose topping is of brick. These are easy to construct and repair. but the surface resulting from these is not smooth and is rough, hence, easily absorbs and retains moisture which may cause dampness in the building.
Method of construction
For constructing a brick floor, the top surface of earth or muram filling is properly consolidated. Over this compacted earth, a layer of clean sand about 10 cm thick is evenly spread. Then a layer of lime concrete (1:4:8) or lean cement concrete (1:4:16) is laid, compacted and cured. Over this base concrete well soaked bricks are laid in cement mortar (1:4) in any suitable bond. In case pointing is to be done, the minimum thickness of joints should not exceed 2 mm and and the mortar in joints is struck off with a trowel. When the pointing is to be done, the minimum thicknessof joints is kept 6mm and the pointin may be done.